So today a gentleman had gone to GPL to invest in a flat there (BTW the going rate is 3800). This individual had made up his mind but came back not investing because he felt some of his questions weren't addressed clearly. Amit Jindal, thanks for talking with me today and sharing this and I am posting it for the benefit of others so that they can share their views and thoughts on the same.
No questions on the quality of the construction, we all agree that its good. But given that EDEN HEIGHTS is nearing possession some of the things become important from a END USER perspective
1. AIR CON Ducting - Looks like GPL is not providing AC DUCTING inside the walls. They will allow the owners to do it 3-4 months prior to possession.
2. Water Supply - HUDA doesn't have any water supply in those sectors so not sure how this will work? Is there additional cost etc? If so what??
3. Sewage - HUDA doesn't have sewer lines in those sectors - how will this be taken care of??
4. Hi-tension wire -- There is also ongoing concern among potential buyers and end users of the high-tension wires those are above one section of the eden heights complex. How does that factor in?
5. Approach road to Eden Heights -- Eden heights is not on the southern periphery road but it's a little away - who is responsible for constructing that road which will connect Eden heights to the main road?
6. Other projects that are just starting construction such as Tulip purple etc are quoting higher prices than Eden Heights - why? given that Eden heights is way ahead from a development perspective.
7. What are the finalized internal fixtures i.e...
All the above are very important questions and I am sure this group will have a lot more of those. SO PLS POST YOUR QUESTIONS...so that we can get some Clarity.
We have a good list of people on this forum and on Amit Shivare's Facebook group - think its time for us to put faces to names and meet !! May be we should plan meeting after Diwali
Happy Diwali to all the members of this group!!!
Cheers
Hello Neighbors - the blog is soon going to be 3 YEARS OLD and that's why the brand new look. The intent continues to be the same i.e connect end users and track progress of the project. Thanks for all your participation and making this forum an important one for all those who have put good money into the Eden Heights project.
Friday, October 22, 2010
Monday, September 6, 2010
Welcome September
Wow!! I got back from the Eden Heights site and I have to admit that i was pleasantly surprised with the way the structures have come up... here are some updates
GOOD STUFF--Brick work going on at all the towers( Tower A - 4bhk ...looks like most of the brick work is done - in other towers the brick work is ranging from 4th floor to the top floor)
CONFUSED ABOUT--. I am still a little confused of the layout of the club house. The gentleman on the site mentioned that the layout model was the most updated but i am not sure....something i will confirm with GPL folks and update here.
CLARITY NEEDED-- . Still no clarity around how GPL plans to use the place where the sample flat is located...i am hearing mixed stuff sometimes i hear its reserved for a couple of very exclusive bunglows. I am also hearing that there could be another mint like tower and i am also hear that there is no plan for that land..it'll be empty. (i like the 1st and the 3rd option - no more mint tower)
4. MATTER OF FACT -- The approach is still from badshahpur village which sticks out like a sore thumb...and i didn't see any work on the SOUTHERN PERIPHERY ROAD...(i don't mean to say there was no work going towards the construction of the road...what i mean is that it not visible from the approach to GPL..)
5. CLARITY NEEDED --- In the scale model of GPL EDEN HEIGHTS shows a 24 meter wide road out side the complex...but what confuses me is that TULIP has apartments coming on both sides of the existing road a few 100 meters prior to GPL and if you drive past the two buildings of Tulip across the current road - you'll wonder how can a 24 meter road be built there...SO THIS IS SOMETHING WE NEED TO FIGURE....
There are still a rare few apartments available from the builder in 2150sqft but all 2,4 and 2190 are sold out. The resale for 2150 is 3200 and 2190 3400 - the word is that the builder plans to jack up the rates further...which should not be surprizing considering the rates in the neighborhood..
hope y'all are doing well.. thanks for keeping the forum very active and informative!!
GOOD STUFF--Brick work going on at all the towers( Tower A - 4bhk ...looks like most of the brick work is done - in other towers the brick work is ranging from 4th floor to the top floor)
CONFUSED ABOUT--. I am still a little confused of the layout of the club house. The gentleman on the site mentioned that the layout model was the most updated but i am not sure....something i will confirm with GPL folks and update here.
CLARITY NEEDED-- . Still no clarity around how GPL plans to use the place where the sample flat is located...i am hearing mixed stuff sometimes i hear its reserved for a couple of very exclusive bunglows. I am also hearing that there could be another mint like tower and i am also hear that there is no plan for that land..it'll be empty. (i like the 1st and the 3rd option - no more mint tower)
4. MATTER OF FACT -- The approach is still from badshahpur village which sticks out like a sore thumb...and i didn't see any work on the SOUTHERN PERIPHERY ROAD...(i don't mean to say there was no work going towards the construction of the road...what i mean is that it not visible from the approach to GPL..)
5. CLARITY NEEDED --- In the scale model of GPL EDEN HEIGHTS shows a 24 meter wide road out side the complex...but what confuses me is that TULIP has apartments coming on both sides of the existing road a few 100 meters prior to GPL and if you drive past the two buildings of Tulip across the current road - you'll wonder how can a 24 meter road be built there...SO THIS IS SOMETHING WE NEED TO FIGURE....
There are still a rare few apartments available from the builder in 2150sqft but all 2,4 and 2190 are sold out. The resale for 2150 is 3200 and 2190 3400 - the word is that the builder plans to jack up the rates further...which should not be surprizing considering the rates in the neighborhood..
hope y'all are doing well.. thanks for keeping the forum very active and informative!!
Thursday, June 17, 2010
June 10 - Eden Heights progress report
Hi ya'll - its been a while. And a lot has happened since my last post and the blog adorns a new look too. Some may like some may not...so pls leave your comments!!!
First off, thanks for all the folks who contacted me via email or by phone and complimented on this blog..your compliments are much appreciated and I am very happy to hear that what we have been able to create with this blog is a genuine community of end users at eden heights. I also got a chance to speak with several of you expressing interest in my own property which i didn't want to part with at this point.
Ajay , Chetan - thanks for your email last night. Well, i feel the eden heights project is doing fairly ok, yes there is delay (builder claims 4-5 months, but i feel its more like a year considering i bought in 2007 with a 3 year window to possession) none-the-less the progress is good. Some of the pointers below will help you make up your mind
The progress report
1. Southern Periphery - YAY! finally the southern periphery road has gotten a go ahead and work has been allocated so hopefully we'll see a brand new road there by mid of 2011. Mohit Bansal very accurately posted the link which i too wanted to post. http://www.indianexpress.com/news/haryana-gives-road-project-to-unitech-dlf/634308/1
2. Tower B and C are constructed till 8th floor (a little behind other towers). Tower I is at 12th floor as of today. All other building structures are completed
3. Brick work and electrical work has begun in most of the buildings.
4. The other bit of news i gather is that GPL folks have some sample designs of villas (remember they originally wanted to make villas at the entrance)which they plan to build at the entrance..I still dont have the layout plans but will try to get those. this is also good news though
5. From a payment perspective - if you were go to by the construction link plan..many folks are sitting at a 95% payment structure..i know quite a few of you have paid upwards of 12 installments and some hovering around 8-9 too. GPL folks are now going less aggressive in seeking for payments.
I haven't gotten a chance to meet with Sandeep or his dad in a long time and it's partly because i haven't tried too hard but I ABSOLUTELY will be meeting them in the next few weeks to get some more insights into the project and share with ya'll. I also plan to visit the site next weekend ( 26th june and hope to share some pics then)
BTW - a very warm welcome to the MINT TOWER users to this site. i am glad you are finding the forum useful to interact.
Lastly, since we have a lot of folks interested in GPL, i am trying to talk to GPL folks to see if folks referring this website can get some discount (this is purely in the interest of genuine users and I am not a broker and seek no benefit from this)
Thanks for your patience and keeping this forum active...QUESTIONS/COMMENTS?????
Vik..
First off, thanks for all the folks who contacted me via email or by phone and complimented on this blog..your compliments are much appreciated and I am very happy to hear that what we have been able to create with this blog is a genuine community of end users at eden heights. I also got a chance to speak with several of you expressing interest in my own property which i didn't want to part with at this point.
Ajay , Chetan - thanks for your email last night. Well, i feel the eden heights project is doing fairly ok, yes there is delay (builder claims 4-5 months, but i feel its more like a year considering i bought in 2007 with a 3 year window to possession) none-the-less the progress is good. Some of the pointers below will help you make up your mind
The progress report
1. Southern Periphery - YAY! finally the southern periphery road has gotten a go ahead and work has been allocated so hopefully we'll see a brand new road there by mid of 2011. Mohit Bansal very accurately posted the link which i too wanted to post. http://www.indianexpress.com/news/haryana-gives-road-project-to-unitech-dlf/634308/1
2. Tower B and C are constructed till 8th floor (a little behind other towers). Tower I is at 12th floor as of today. All other building structures are completed
3. Brick work and electrical work has begun in most of the buildings.
4. The other bit of news i gather is that GPL folks have some sample designs of villas (remember they originally wanted to make villas at the entrance)which they plan to build at the entrance..I still dont have the layout plans but will try to get those. this is also good news though
5. From a payment perspective - if you were go to by the construction link plan..many folks are sitting at a 95% payment structure..i know quite a few of you have paid upwards of 12 installments and some hovering around 8-9 too. GPL folks are now going less aggressive in seeking for payments.
I haven't gotten a chance to meet with Sandeep or his dad in a long time and it's partly because i haven't tried too hard but I ABSOLUTELY will be meeting them in the next few weeks to get some more insights into the project and share with ya'll. I also plan to visit the site next weekend ( 26th june and hope to share some pics then)
BTW - a very warm welcome to the MINT TOWER users to this site. i am glad you are finding the forum useful to interact.
Lastly, since we have a lot of folks interested in GPL, i am trying to talk to GPL folks to see if folks referring this website can get some discount (this is purely in the interest of genuine users and I am not a broker and seek no benefit from this)
Thanks for your patience and keeping this forum active...QUESTIONS/COMMENTS?????
Vik..
Thursday, April 15, 2010
Aggressive Payment plan, delay in schedule, flats for sale
Friends I apologize for no update in a while...i have been out a lot and tehrefore not getting a chance to vist the site nor the builder. So i am hearing a few things
a. Aggressive payment plans -- what the builder is doing is sending letters based on per tower completion of work per tower and if you visit the site you'll notice that some towers are moving very aggressively compared to others
2. Delay - I visited the site about a month back..work is going well but i am concerned about the delay in possession. Technically the possession should be oct 2010 (given that they launched the project in oct 2007)..but I am not sure we should expect it before oct 2011. i.e i am still not sure what will come up where the current show-house is...earlier it was the villas and now..??
3. Those interested in buying flats ..i know of a couple of folks who may be seling...(i am not sure yet but I may also consider too as I am looking at buying another which is ready to move in near my kids school) -- pls let me know via email if someone is interested...vix_bh@yahoo.com
4. good news is that the southern periphery road work is soon begining which will finally connect golf course extn to haldirams
Photos to come
vik
a. Aggressive payment plans -- what the builder is doing is sending letters based on per tower completion of work per tower and if you visit the site you'll notice that some towers are moving very aggressively compared to others
2. Delay - I visited the site about a month back..work is going well but i am concerned about the delay in possession. Technically the possession should be oct 2010 (given that they launched the project in oct 2007)..but I am not sure we should expect it before oct 2011. i.e i am still not sure what will come up where the current show-house is...earlier it was the villas and now..??
3. Those interested in buying flats ..i know of a couple of folks who may be seling...(i am not sure yet but I may also consider too as I am looking at buying another which is ready to move in near my kids school) -- pls let me know via email if someone is interested...vix_bh@yahoo.com
4. good news is that the southern periphery road work is soon begining which will finally connect golf course extn to haldirams
Photos to come
vik