Thursday, April 15, 2010

Aggressive Payment plan, delay in schedule, flats for sale

Friends I apologize for no update in a while...i have been out a lot and tehrefore not getting a chance to vist the site nor the builder. So i am hearing a few things

a. Aggressive payment plans -- what the builder is doing is sending letters based on per tower completion of work per tower and if you visit the site you'll notice that some towers are moving very aggressively compared to others

2. Delay - I visited the site about a month back..work is going well but i am concerned about the delay in possession. Technically the possession should be oct 2010 (given that they launched the project in oct 2007)..but I am not sure we should expect it before oct 2011. i.e i am still not sure what will come up where the current show-house is...earlier it was the villas and now..??

3. Those interested in buying flats ..i know of a couple of folks who may be seling...(i am not sure yet but I may also consider too as I am looking at buying another which is ready to move in near my kids school) -- pls let me know via email if someone is interested...vix_bh@yahoo.com

4. good news is that the southern periphery road work is soon begining which will finally connect golf course extn to haldirams

Photos to come

vik