Hello Neighbors - the blog is soon going to be 3 YEARS OLD and that's why the brand new look. The intent continues to be the same i.e connect end users and track progress of the project. Thanks for all your participation and making this forum an important one for all those who have put good money into the Eden Heights project.
Thursday, November 26, 2009
1500 and 2190 going for 3000 PSFT
The good news is that there is sudden uptick in demand and the new sectors are seeing it too. Let me focus on Eden Heights progress
1. Flats sized 1500 and 2190 are now being sold for 3000 psft (YAY!! finally some reason to cheer).
2. Flat 2150 - is being offered at 2800 psft.
3. Launch of penthouses on the top-floor- the design work is not finalized yet but the size is going to be a ballpark 3500Sqft and these apartments will be priced differently.
4. Possession is expected before the close of 2011 (delayed --- 2 more years..a little disappointing considering that i made the booking in Nov 07 - 4 YEARSS as opposed to promised 3 years at the time of booking...while this is expected in India but I hope its no longer than that!!)
5. I visited the site a few weeks back and the quality of work being done seems good - which is encouraging.
I am still n ot sure of what GPL groups strategy is with the land they had initially kept for villas - I wont be surprized that if market is upbeat then we might seem those villas being offered.
Hope you guys have a great rest of the year.
Vik
Sunday, October 4, 2009
Back!!! visit to the Eden heights site and pictures
Long time, no excuses for being away. Call it the FY'10 planning blues or simply being distracted with other things - including baby managements (guess you guys know I have 2 toddlers - one is 2.5 yrs and the other turning 1 next month). We'll i'll not bore you to death with my personal details so getting to the point
> Wow!! there seems to be a lot of renewed interest in real-estate market and in sec 69-70 too. there is
-- Unitec Sunbreeze (sec 69/ 2800PSFT approx)
-- Unitec Vista (sec 70/ 2750 PSFT approx)
-- Tulip Whites (sec 70 - not sure whats the rate)
-- DLF Corporte greenes - Sec 74
-- Tulip orange - Sec 69
-- The land next to eden heights is reserved for Tata housing..but their plans are not yet on the horizon
> there is a tremendous activity on the golf course extention road.
-- pioneer park
-- MGF emrald
-- IREO
-- Palm drive sec 66 is coming up really well but need about 2+ cr to get that.
ok. here are the pics
Tower A - 4bkh - almost done upto 3rd floor
Tower B and C - Basement raft work is going on
Tower D and E - 4th floor is under progress
Tower F and G - 4th floor is under progress
Tower H - Ground floor is under progress
Tower I - basement raft still un progress
i have tried to identify the towers so you guys see it clearly.
ONE concern I have
the gap between towers is not more than 2-3 feet..which seems so small and almost scary. I am sure the civil guys have done some research - but it looks ugly and one can jump from one balcony to another if you have one of the 2150 sqft apartments. i'll speak GPL folks and get their reasoning.
Bottomline - work is going on but not at a pace i'd have liked - nonetheless there is progess. MINT Towers are almost sold out so good thing is that GPL folk have cash flow.
What other things have you heard??...here is the latest link to the pics
http://picasaweb.google.co.in/vikrant.bhatnagar/EdenHeightsOCTOBER2009#
Sunday, August 16, 2009
mint towers and eden heights
a. low cost apartment
b. volume (8 flats on each floor..ouch!! thats a lot)
c. lot of press and visibility by means of hoardings etc which is also creating more visibility for eden heights
what i am not particularly impressed about is
a. I feel this compromises the "luxury" promise of the Eden heights
b. mint tower is at the entrance and there is still a lot of place open (where vilas were planned - what happens to those - MORE low-cost towers??? - hope not!!)
c. Gentry of the complex
d. pricing of mint towers
anyway, looks like construction is going well for the rest of the eden heights.
amit - your message in the last post about tower D - i am not sure if folks have receive the note for fifth installment for tower D...hope to have someone responding to this note
cheers
Friday, June 26, 2009
Pictures of GPL...
Thanks Amitabh for sharing these pics..please keep 'em coming!!!
the web album on your left is also updated with these pictures and also those pictures that Manish (GPL sent)...check them out


Saturday, June 13, 2009
Update - meeting with Sandeep and Mr KL Gupta
1. They have hired a dedicated CEO to focus on the Eden Heights project (which continues to be a brand building, flagship project for them). Though I don't remember the name of the guy but according to Sandeep, the CEO comes with very good credentials and was responsible for completing some Mahindra's project in faridabad ahead of time... YAY!!
2. Mr KL Gupta explained to me why we were seeing different progress in different towers
- he said that it was not practical to make all towers at the same time and we'll never find a construction project working that way.
- They are focussed on getting the building higher so that work can continue at a rapid pace even during monsoon - which made sense to me
- they have 2 contractors among whom the project is distributed - this helps in healthy competition, less dependancy on one, and higher quality - and sometimes this also leads to differnt pace in differnt towers
3. Both Sandeep and his dad were confident that the next 6 months would give all us better visibility of the project and we will definitely see work only getting faster and building coming up quickly from hereon
4. They are committed to the eden heights project and when i asked about date of completion - they acknowledged that there has been some delay (due to some licenses - now they have all) and will be able to tell us a fair date of possession in the next 6 months. They are very confident that the project will be delivered sometime during 2011...(that is what most of us thought when we took a poll on this site about 6 months back)...so obviously we need to stay clued on.
5. Villas- I was actually pleasently surprised when Sandeep said that they were assessing if the current economic times made sense for them to build vilas' and were re thinking the strategy for that land - it could be floors - its all on the drawing board but more to come.
6. Both Sandeep and Shree KL Gupta - sounded confident with the bank support to complete the project even if 100% sale was not achieved. They, however, did highlight that it was important for them to keep receiving funds/payments from end users so that they have working capital to keep the project moving -- which makes sense to me.
Bottomline - Like most of you, I too feel encouraged everytime I meet Sandeep and his dad and I am hoping that they will live upto the expectations and committments we have of them and the project.
I am writing this post in a little hurry but I think I have covered most of what I discussed with them and incase i remember more i'll make sure to update...NOW lets see what questions/comments you guys have. Teekam, i know you were visiting the site today, any updates??? Samir, hope you had a good trip back...
cheers guys
yours - Vik